Tuesday, August 31, 2021

Dhaka Metrorail has Completed Performance Test


The people witnessed the official test run of Metrorail on the line (MRT Line-6) lay on the flyover (viaduct) on 29 August, 2021. The experimental operation started from the depot built for Metro Rail in Dhaka's Uttara. Road Transport and Bridges Minister Obaidul Quader inaugurated it. NM Siddique, Managing Director, Dhaka Mass Transit Company Limited (DMTCL), a representative of the Japanese Embassy in Bangladesh, the head of JICA Bangladesh office and a representative of Metrorail's consulting firm were present on the occasion.

As soon as the train started running slowly over the flyover immediately after the inauguration, the present government officials, employees, technicians, engineers and media persons standing on both sides of the line observed the rail movement. At this time many people applauded and applauded. Many people take photos with the train to capture the memory of this historic moment, including taking pictures and videos of experimental train movements.


At this time, the security personnel had to work hard to handle the crowd. This Metrorail runs on electricity through the connection of a power transmission line placed on a lovely pillar above the line. Minister for Road Transport and Bridges Obaidul Quader said Prime Minister Sheikh Hasina will inaugurate three mega projects in the year 2022. In June the Padma Bridge, later the Karnafuli Tunnel and the Metrorail Line-6 which is the dream of the young generations, will be inaugurated at the end of the year. "It's a milestone," he said. Metrorail is no longer a dream, it is a visible reality. Critics will criticize and propagate, we will respond at work. The Sheikh Hasina government responded. We are responding by constructing mega projects including Metrorail and Padma Bridge.


The minister said that it would take six months to complete the work of Metrorail Line-6. Total work has progressed 68.29 percent till July 31 for the MRT-6. Work progress from Uttara to Mirpur is 88 percent. The minister recalled, "I came to see the depot work progress activities and suffered from fever for three days due to rain felled in my face." But today, it is very good that Sheikh Hasina's contribution, Metrorail is visible. This movement is passenger less. The train will run experimentally between four stations from Uttara to Mirpur Pallabi in the capital. This movement is called 'performance test'.


Total number of 24 sets of trains will run on Metrorail-6 route from Uttara to Agargaon. In the meantime, four sets of trains have already arrived in the country. The first set of trains reached the depot in Dhaka last April. Each of these trains consisting of six carriages, made the trip from its depot and back after crossing three stations on its way without any passengers. Each train can carry a maximum of 2,308 passengers at a time. The trains are being manufactured by Kawasaki Heavy Industries Limited of Japan. Later the trains were brought to the country by ship from the seaport of Kobe in Japan.


The overhead construction of metro rail can help the Bangladeshi government's efforts to ease traffic gridlock in Dhaka. Once the project is implemented, a train with six air-conditioned spacious coaches will operate every four minute and will carry some 60,000 passengers each hour. The MRT Line-6 consists of 16 elevated stations and electricity-powered light rail tracks. In addition, total six Metrorail routes will start within 2030.

 

Thanks,

 

 

Related:

Subway Rail System in Dhaka City

LRT | Light Rail Transit Services in Narayangonj

Dhaka - Jashore in Two and Half Hoursvia Padma Bridge

Faridpur Bhanga to Mawa Rail Line

Dhaka City Metro Rail MRT Line 6 willstart in 2019

Dhaka-Ishwardi- Benapole Dual GaugeRail Route

Rupsha Railway Bridge in Khulna-Mongla Rail Line

Dhaka to Kurigram Direct Express Train

Dhaka - Chattogram Double Track Railway Update

Dhaka-Mawa-Bhanga Expressway has been Inaugurated

Master Plan around Karwan Bazar